Stoffer Hall - Project Budget
The most recent budget approved by the Board of Regents on July 28, 2006 when the construction contract was awarded to Ferrell Construction Company.
Construction Costs
- $10,487,000 - Base Construction
- 724,788 - Alternate Construction
- 845,687 - Construction Contingency
- $12,057,475 - Total Construction Costs
Other Project Costs
- $ 486,000 - Telecommunication Design
- 622,000 - Furnishings & Equipment
- 400,000 - Equipment
- 75,000 - Security
- 1,017,823 - Architectural/Engineering/Laboratory Fees
- 18,638 - Testing, Inspection, Soils, Surveys
- 24,851 - Permits & Miscellaneous
- 250,000 - Hazardous Material Abatement
- $ 2,894,312 - Total Other Costs
Total Project Budget
- $14,951,787 - Total Project Budget