Stoffer Hall - Project Budget

The most recent budget approved by the Board of Regents on July 28, 2006 when the construction contract was awarded to Ferrell Construction Company.

Construction Costs

  • $10,487,000 - Base Construction
  •        724,788 - Alternate Construction
  •        845,687 - Construction Contingency
  • $12,057,475 - Total Construction Costs

Other Project Costs

  • $      486,000 - Telecommunication Design
  •        622,000 - Furnishings & Equipment
  •        400,000 - Equipment
  •          75,000 - Security
  •   1,017,823 - Architectural/Engineering/Laboratory Fees
  •          18,638 - Testing, Inspection, Soils, Surveys
  •          24,851 - Permits & Miscellaneous
  •        250,000 - Hazardous Material Abatement
  • $  2,894,312 - Total Other Costs

Total Project Budget

  • $14,951,787 - Total Project Budget