Athletics Conditioning Center

Options and Comparisons

These options and comparisons were presented to the Washburn University Board of Regents Budget and Finance Committee on January 16, 2007. The conversion of Whiting includes the addition of a new second floor basketball court and two floors of classroom/office space of up to 17,000 sq. ft.


Convert Pool
Convert Whiting
Square Footage 26,875 sq ft
35,000 sq ft
Costs $2,869,625 Construction $2,998,000

143,000 Contingency 149,900

143,000 Inflation 149,900

400,000 Equipment 400,000

275,000 Professional Fees 275,000

$3,830,625 Total Project $3,972,800
Deduct Options -937,500 2nd floor


3rd fl framing -150,000

-609,375 New addition
Phasing Option -629,000 Remodel locker rooms -750,000
Lowest Cost $1,654,750
$3,072,800




Source of Funds


Fundraising $2,500,000
$2,500,000
WU reserves $ 0
$572,800

The following advantages and disadvantages were provided for each option:

Pool conversion - Advantages
  • Pool eliminated
  • Lowest cost
Pool conversion - Disadvantages
  • Pool closing wil be an issue
  • Separates football conditioning and lockers
  • Pool usage has increased over past 18 months
Whiting Conversion - Advantages
  • Pool remains viable facility
  • Project addresses Whiting deficiencies (floor, A/C, windows, doors, ADA)
  • Fundraising potential as historic restoration project
  • Plenty of available space could provide classrooms or office space
  • Conditioning area close to football locker rooms
Whiting Conversion - Disadvantages
  • Existing capital maintenance needs add to cost of project
  • Pool will eventually require capital maintenance
  • University reserves required to add new academic space, electrical upgrades, etc.