WEA Relocation - 1729 MacVicar Renovation

Actual Compared to Budget - as of December 31, 2006



 

Account

Name

Actual

Budget

Balance

Purchase   Kirk & Cobb Realtors $234,060 $235,625 $1,565
           
Construction   DF Osborne Construction $1,546,000 $1,546,000 $0
           
Architect/Engineering          
    Bartlett & West Engineers 6,619    
    Latimer Sommers & Assoc 6,875    
    Schwerdt Design Group 18,244    
    Terracon 12,403    
    William Sheahan Assoc 107,790    
    Subtotal: $151,931 $123,680 $28,251
           
Reroute Sewer   Herman's Excavating $27,250 $27,500 $250
           
Soft Costs          
  Space Rental BTC - Jan 10    
  Other Fees KS Board of Tax Appeal 50    
  Professional Fees Robert C Taggart & Assoc 300    
  Printing Topeka Blueprint 9,507    
  Insurance IMA of KS 9,270    
  Land Improvements Terrapin Landscaping 1,740    
  Property Tax Refund Shawnee Co -1,039    
  Telecommunications Computer Cable Connection 22,635    
    SBC Communications 11,416    
    Torgeson Electric 56,000    
  Fire Alarm System SimplexGrinnell 3,915    
Total Soft Costs     $113,805 $334,600 $220,795
           
Total Project Costs     $2,073,046 $2,267,405 $194,359